Infrastructure

Project Title : Al Zour North Water Distribution Complex and Mina Abdallah Water Distribution Complex
Location : Al Zour and Mina Abdallah
Client : Ministry of Electricity and Water
Cost : 300 M KWD
Size : 1, 060, 800 m2
Duration : 2006 - 2015

Azzour North Water distribution Complex and Mina Abdullah Water distribution Complex (1,060,800 m2) and the transition from and to both of them (160 KM total length) Including all design of Infrastructure services, Architecture, Structure, Mechanical, HVAC, Lighting, Tel, and etc. for All the building located inside the site (Pump station building, Chlorination Building, stand by Generator Building, Sub-Station Building... etc.).


1. WDC II (Minaa Abdulah Complex)
2. 3 Pipe lines x 1600mm from Minaa Abdullah to west fanitees

  • Study and design of Al-Zour North Water Distribution Complex and Mina Abdullah Water Distribution Complex
  • A Total Area of 1,060,800 m2
  • A Total Length of 160 Km between both sites (Al Zour and Mina Abdullah).
  • The project includes several buildings in addition to the distribution complex, including but not limited to:
    • Pumping Station
    • Chlorination Building
    • Standby Generator Building
    • Sub-Station Building
    • Employee Offices

 Dar Al-Dowailah Engineering Consultants & Construction Managers Role is the

  • Complete Data Collection
  • Complete Concept Design of all project components
  • Complete Detailed Design of all project components
  • Preparation of Tender Documents and Bills of Quantities